Client:
Chmelnitski “SPETSKOMUNTRANS” utility company
Project name:
Closure and reclamation of the existing landfill that does not meet
Closure and reclamation of the existing landfill that does not meet current engineering requirements, as well as the construction of two new sanitary landfill cells
Closure and reclamation of the existing landfill that does not meet current engineering requirements, as well as the construction of two new sanitary landfill cells
Contractor:
Mesogeos S.A – Hayat Group
Start date: 14.12.2024
End date: 14.12.2026
Financial İnstitution:
EBRD
Project cost:
12.449.143,00 EURO